Project Factory
Work Scope:
Factory building construction 3 columns line at 20m each spans, one office story reinforce concrete slab under steel roofing sheet I-Lock
Works include:
- Foundation: Piling works, Pile Cap
- Reinforce Concrete Work: Ground beam, ground slab, column, FF beam and slab and roof beam
- Steel Structure Work: Steel column, roof truss, roofing sheet, steel door & window
- Finishing Work: Interior & external block wall and plastering works and floor finish, wall painting finished and external works
Garment Factory Project
Factory size 66 x 60 m, office size 12 x 60 m
Location: Trapaing Thleung, Khan Ressey Keo, Phnom Penh
Client: Mr. Peng Seng
Contract Duration: 7 months
August 2009 ~ February 2010 (Complete)
Project Contract Value: $US 24,000.00